Industrialised construction against conventional building: what changes in quantities, cost and programme

Illustration: four residential towers on retail floors, luxury specification, with a pool on the retail roof

Industrialised construction is building in which part of the work moves from the site to a factory or to reusable formwork: precast elements, prestressed hollow-core slabs, system formwork for casting on site, and up to modular concrete units that arrive almost finished. For the bill of quantities (BOQ) this is a real change: instead of m³ of concrete, m² of formwork and tonnes of rebar, the BOQ shows components by number or by m², transport, lifting and connections. I have experience in quantity takeoff for industrialised construction and precast elements, and in comparing them with casting on site.

Three levels of industrialised construction

Not all industrialisation looks the same. The more work moves to the factory, the shorter the site part of the BOQ becomes and the longer the component items get.

Levels of industrialisation and how they look in the BOQ
LevelWhat moves to the factoryHow it looks in the BOQ
System formwork, cast on siteThe formwork onlym³ of concrete and m² of formwork as usual; the reusable formwork affects the price and the pace
Precast elementsMaking the component: walls, beams, stairs, hollow-core slabsNumber or m² by type, thickness and length; beams in m³ by cross-section
Modular concrete unitsAlso building services, windows and part of the finishesA complete unit, transport, lifting, connections and completion work on site

A modular concrete unit is structural reinforced concrete, not light steel framing. The difference is explained on the light steel framing versus blockwork page.

What changes in the BOQ: chapter 02 against chapter 03

Casting on site is measured under chapter 02 of the General Specification for building works, Israel's inter-ministerial specification: concrete, formwork and reinforcement. Precast components are measured under chapter 03, where the rules are different:

The particular specification of my graduation project also stated that concrete that runs into the cores of the slabs at their ends is not measured, and that a strip wider than 50 cm between slabs is measured as a full-thickness slab. Details like these move quantities, so I read them before pricing.

Illustration: a high-rise residential building, about 14 floors, with green balconies facing a park and a lake

Worked example: one m² of cast slab against one m² of hollow-core slab

For illustration, a 20 cm cast slab against a 20 cm hollow-core slab with a 5 cm topping, per m² and for a floor of 400 m²:

Site quantities per m² and for a 400 m² floor (for illustration)
ComponentCast slab, per m²Hollow-core slab, per m²Cast floorHollow-core floor
Concrete on site, with 4% waste0.208 m³0.052 m³83.2 m³20.8 m³
Formwork1 m²Per the propping detail400 m²Minimal
RebarAbout 20 kgAbout 2.5 kg of mesh8,000 kg1,000 kg
Precast component–1 m²–400 m²
LiftingA pump on the day of the pourA crane for all the slabsA pour dayCrane days

The rebar in the cast slab is calculated at 100 kg per m³ times 0.2 m³. The mesh in the topping is 6 mm bars at 20 cm centres in both directions: 10 m of bar per m², times 0.222 kg per metre, and with laps about 2.5 kg. Concrete on site drops by about 75%, and the formwork almost disappears. But the cost does not disappear: it moves from the site to the component item, to transport and to the crane.

How to compare costs fairly

Compare a finished floor with a finished floor: components, transport, lifting, connections, topping and infill pours, against concrete, formwork, rebar and labour. Then add time. According to a 2018 business article that reviewed studies in Israel, partial industrialisation shortened construction by about 32%, and full industrialisation shortened the structural frame time by about 44%. The same article stated that in a nine-storey building the structural frame is about 16% of the construction cost and about 35% of the construction time, about seven months.

For illustration only: if seven months of frame work are shortened by 44%, that is about three months. With site overheads (preliminaries) of 60,000 shekels a month, the difference is about 180,000 shekels, and it has to go into the comparison next to the price of the components. The full calculation of overheads is on the site overheads page.

What to check in a quote: whether the price per component includes transport, lifting, connections, topping and infill pours. Under chapter 03 each of these can appear as a separate item, and comparing an all-inclusive price with a manufacture-only price is comparing apples with oranges.

When industrialised construction pays off

In short: a design frozen early, repetition and good crane access → precast. Late changes, an unusual shape and a cramped site → casting on site.

For a price comparison per m³ between casting on site and precast, see concrete frame cost. And for the method in which the formwork stays in the wall as insulation, see insulated concrete forms.

In industrialised construction, the quantity takeoff moves from the site to the factory: you count components, not m³ of pour. A quantity surveyor who knows both methods can compare them on the same basis.

Frequently asked questions

Is industrialised construction cheaper?

Not always. The price of a component is higher than the price of the concrete alone, and the difference can be offset by time, overheads and less work on site. Only a full comparison, like the example above, gives an answer for a given project.

What is the difference between precast and a modular unit?

A precast component is a part: a wall, a beam or a slab. A modular unit is a room or a part of a building, including services and finishes, that arrives ready to be lifted and connected.

How is a hollow-core slab measured in the BOQ?

In m², stating the type, the concrete grade, the thickness and the type of prestressing. The topping and its reinforcement are measured separately. Contractors' units of measurement are covered on the pricing units page.

Who does the quantity takeoff for this kind of construction?

A quantity surveyor for construction projects who knows both chapters and can compare a finished floor with a finished floor.

Have a project? Tell me briefly what the project is and what already exists. When the project is a good fit, I usually reply with focused questions and a written quote.

Contact me for a quote

More on this site

* Created with AI for marketing, for illustration only. Not reviewed by Yaakov Avital and not professional advice. Every project must be checked on its own by a professional quantity surveyor and an engineer.